The State of the Denver Site Development Plan: 2017 Edition

Site Development Plan

I wrote this article roughly 2 years ago intended as an outline for the Site Development Plan (SDP) process in City of Denver. A client recently asked if the article was still accurate and I realized that it needed some revisions!

Altitude Land Consultants (ALC) has felt the boom of the Denver market. ALC has prepared 80+ Site Development Plans in Denver in the last 5 years alone! My team, one of three at ALC, has 10-15 Site Development Plans tracking at any given time at the City. With that much volume, I have my fingers on the pulse of the City’s constantly moving process and what you can expect as a developer/architect/owner.

So, what can you expect?! The short answer is you can expect approval of your Site Development Plan in roughly 5-6 months from your concept submittal (depending on your project coordinator at the city). Two years ago, I would tell my clients to expect roughly 4 months. It’s bumped out a bit. The volume of submittals alone to the city is pushing out typical review timelines.

What does the process look like?

Step 1: Submit concept plan and application

Your project receives a project number and the City staff will review your intake submittal and schedule a meeting. Additionally, you are assigned a City Project Coordinator based on the location of your project and the staff’s workload. Generally, you will have your concept meeting within 2 weeks of submitting application and expect comments back from the City roughly 2 weeks after that.

I’ve been on several of projects that don’t include the civil engineer in their concept meeting. Here’s my advice: INCLUDE YOUR CIVIL ENGINEER IN THIS PROCESS. Your civil engineer will know many of the questions and follow-up questions to ask the reviewers in that meeting. This will help avoid issues in your concept submittal. Additionally, I recommend having a civil engineer look at your concept site plan to ensure there’s no obvious issues.

Your concept comments from this meeting should be used as the framework for your first Site Development Plan submittal. The reviewers will advise what supplemental processes are required as well.

Step 2: Submit SDP

City of Denver will clear you to go to Site Development Plan once all conceptual level Concept Plan comments are cleared. The Site Development Plan process can take a couple of different directions. Based on the comments received in Concept, you will know what your Site Development Plan process will look like. At this point, I highly recommend deciding who will ‘quarterback’ the submittal process with the City. I tend to recommend myself as the quarterback and do the task without additional fee. I just find things go more smoothly if I’m able to act as the conductor on the Site Development Plan side of things.

The first, and always, required portion is the Site Development Plan itself. This is a construction level set of drawings that show detailed site grading, utilities, layout, drainage, photometric, architectural elevations/floorplans and landscape as well as a Survey sheet which must be prepared and stamped by a Colorado Licensed Land Surveyor (REMINDER: Altitude Land Consultants offers civil, landscape, photometric and surveying). In addition to the Site Development Plans, there are 6 others potential plans/processes that might accompany it: Sewer-Use and Drainage Permit, Transportation Engineering Plan (TEP), Wastewater Construction Drawings (SSPR), Stormwater Construction Drawings, Denver Water Review, and/or Storm Water Management Plan.

Sewer-Use and Drainage Permit (SUDP):
An SUDP is required with all new building construction for EACH building. An SUDP is required on all Site Development Plan submittal. This process runs concurrently with your SDP review. This permit is obtained from the City’s Wastewater Department. These permits are typically obtained within an 8 week period if SSPR is not required. It can run quicker and can greatly vary on which SUDP reviewer you are assigned. The SUDP set must be prepared by a licensed engineer and include site layout, addressing, grading, utility design and any calculations associated with the design. If you are proposing a finished floor elevation less than 24” above adjacent flow line, you will also be required to provide a flood study.

As the developer, you should also be aware that you will need a geotechnical report to submit with these plans along with the plumbing plans for the building. The city will NOT accept your SUDP submittal without SUDP Plans, Geotechnical Report (dated within the last 6 months) and FOR CONSTRUCTION plumbing plans/footprints with fixtures. Additionally, you are required to cut-off any existing sanitary sewer lines to buildings to be demolished prior to issuance of permit/approval. Also, the fees can be significantly costs ranging from $15,000 to $40,000 (and even higher) per building depending on the project’s sanitary sewer tap size and demand.

Additionally, you will need to submit a fixture count spreadsheet to Denver Water to get your domestic tap size required. You will get a stamped copy of your utility plan from Denver Water and include that plan in your submittal to SUDP as well. This is not required for intake, but it is proactive to provide if possible.

Transportation Engineering Plans (TEP):
The TEP is another one of the most common requirements when doing an infill project in Denver. As part of your construction, you will be required to replace any adjacent, damaged infrastructure such as sidewalk, curb, and alleyway. It’s quite common to be required to remove and replace adjacent alleyway and this will trigger a TEP process and review by the City’s Transportation department. Transportation will also review all ADA ramps located adjacent to your site. The TEP process runs concurrently with your Site Development Plan review and typically takes 8 weeks to receive approval.

Wastewater Construction Drawings (SSPR):
The wastewater construction plans must be approved by Denver Wastewater Department. These plans become a requirement when doing any proposed public/private sewer mains as well as any major sanitary sewer items (i.e. pump stations). As the developer, you are allowed one sanitary sewer service header per building without triggering this requirement. The plans generally include all site, grading, utility layout and include plan and profiles of the proposed sanitary line.

Stormwater Construction Drawings:
This is like the wastewater construction plans but for Stormwater design. This design is reviewed by the Wastewater Department. The deliverables on this process consist of a set of stormwater design plans as well as a drainage report and calculations. You will need to meet all the requirements of the Denver Stormwater Triage checklist. This checklist can be found in the Storm Drainage Design & Technical Criteria Manual. These plans become a requirement if your project contains a detention facility, water quality, storm infrastructure, or any other major stormwater infrastructure.

Denver Water Review:
Denver Water won’t make comments or review your conceptual plans. This can be frustrating if you are a new developer and it’s one of the common mistakes I see new developers make. They will go through the Site Development Plan process not realizing they needed Denver Water approval on a portion of their project through separate process. Generally, Denver Water plans will be required if you are doing a water main extension or providing a dedicated fire line to your building. If you are pulling your sprinkler off a domestic line, Denver Water is not involved at this time.

Denver Water will require a set of plans to their standards along with demand calculations for any fire line or main you will be constructing. This can create issues on fire lines since many times those are completed design-build during construction by the fire line consultant. In these cases, I recommend my client reach out to their fire line consultant to get an estimate for the demand and size based on their experience. Many times that will be enough for first submittal and can be amended once the system is fully designed.

Denver Water process also has a review fee and inspection fee associated with it. These are generally around $1200 together. On top of that, the developer will have to pay tap fees associated with the domestic tap per Denver Water rates. Dedicated fire lines do not have a tap fee associated with them.

You do not need Denver Water approval for your SDP approval, so many times this can be the ‘last horse’ to cross the finish line in your process. You just can’t start any of your water improvements until approval is completed.

Storm Water Management Plan (SWMP):
A SWMP is required in Denver if you disturb over an acre of land in your development. Let me clarify that this is NOT a catch-all rule. I’ve seen sites smaller than an acre get forced into a SWMP due to being “High Risk”. These sites found asbestos while excavating and were, therefore, required. The SWMP deliverables are a narrative and erosion control set of plans. This will be the plan in which your contractor shall follow to ensure that no downstream properties are polluted by your development. A SWMP is sometimes called a Stormwater Pollution Prevention Plan (SWPPP) in other jurisdictions. City of Denver will review your SWMP for completeness and sometimes provide comments.

There are many times a number of deliverables required by the City of Denver on any new construction. One of the most important things you can do as a new developer is to find a design team who you can trust and knows the jurisdiction. In the City of Denver, ALC is a trusted design team to dozens of both seasoned and not-so-seasoned multifamily developers and architects who expect a smooth process through City of Denver’s Site Development Plan requirements. Our project managers have worked with every project coordinator/reviewer at the City and have the experience to get approval as quickly as possible.

Altitude Land Consultant has all the teams in-house to get you through Site Development Plan (except for architecture). We will help you navigate this process with greater ease, eliminate costly mistakes and loss of time during the most vulnerable phase of your project.

City of Denver Site Development Plan Process

If you live in Denver or have driven through it recently, you probably are more than aware that multi-family development is BOOMING in the City of Denver. I will use the word “multi-family” to define any apartment, townhome, or condo development. If the current City of Denver forecast is anything close to reality, this boom is here to stay for the next 5+ years.

BLVDBuilder-096

This environment is making profitable opportunities for not just the big developers but also many first time developers. This article is written more towards the developers (or potential developers) who want to start developing in Denver but have little or no experience in the City. Even the most seasoned developers can find frustration in the City of Denver development process that is associated with these projects. It’s immensely important to ensure your Civil Engineer (and design team) has the knowledge and experience to anticipate most of the things Denver will throw at you in the process.

The Denver development process generally consists of the following steps:

Step 1: Concept Plan
Concept Plan is the precursor to your formal site plan submittal. This is the City’s way of filtering out projects that have no chance of succeeding before the owner spends unnecessary money. This process will require a relatively basic level site drawings and elevations (at a minimum). Many times the city will require more detail if you trigger one of their other requirements. For example, if your lot is over 0.5 acres disturbed (not just in size), you will also need to include a drainage plan showing preliminary detention calculations. There’s several other items that can come up which might also require a preliminary utility plan.

I always recommend to my clients that we bring in a preliminary grading, utility and drainage plan along with preliminary architectural elevations to ensure we rout out all potential issues that the City might have. You will then attend a “Concept Plan Meeting” at City of Denver’s Webb Building downtown. Denver will assign you a planner to review your project and shepherd you through the process. The “Concept Plan Meeting” will have representatives from Denver’s review agencies: Fire, Zoning, Wastewater, Survey and Planning.

These agencies will provide you with approval or denial based on the materials and design you provide to the City. These comments will range from minor clarifications to complete deal killers. If you are denied on a minor clarification, we will just update the plans and re-submit. Assuming you’ve addressed all the conceptual concerns, its time to go to Site Development Plan.

Step 2: Site Development Plan
City of Denver will clear you to go to Site Development Plan once all conceptual level Concept Plan comments are cleared. The Site Development Plan process can take a couple of different directions. Based on the comments received in Concept, you will know what your Site Development Plan process will look like.

There are several other potential plans that you will need to get approved in this step. The first, and always, required portion is the Site Development Plan itself. This is a construction level set of drawings that show detailed site grading, utilities, layout, drainage, and landscape as well as a Survey sheet which must be prepared and stamped by a Colorado Licensed Land Surveyor (REMINDER: Altitude Land Consultants offers civil, landscape and surveying). In addition to the Site Development Plans, there are 6 others plans/processes that might accompany it: , Sewer-Use and Drainage Permit, Transportation Engineering Plan (TEP), Wastewater Construction Drawings (SSPR), Stormwater Construction Drawings, Denver Water Review, and/or Storm Water Management Plan.


Sewer-Use and Drainage Permit (SUDP):
An SUDP is required with all new building construction for EACH building. These permits are obtained from the City’s Wastewater Department. Generally speaking, these permits are quickly obtained within a 4-6 week period if SSPR is not required. The SUDP set must be prepared by a licensed engineer and include site layout, addressing, grading, utility design and any calculations associated with the design. As the developer, you should also be aware that you will need a geotechnical report to submit with these plans along with the plumbing plans for the building. Additionally, you are required to cut-off any existing sanitary sewer lines to buildings to be demolished prior to issuance of permit/approval. Also, the fees can be significantly costs ranging from $15,000 to $40,000 (and even higher) per building depending on the project’s sanitary sewer tap size and demand.


Transportation Engineering Plans (TEP):
The TEP is another one of the most common requirements when doing an infill project in Denver. As part of your construction, you will be required to replace any adjacent, damaged infrastructure such as sidewalk, curb, and alleyway. It’s quite common to be required to remove and replace adjacent alleyway and this will trigger a TEP process and review by the City’s Transportation department.


Wastewater Construction Drawings (SSPR):
The wastewater construction plans must be approved by Denver Wastewater Department. These plans become a requirement when doing any proposed public/private sewer mains as well as any major sanitary sewer items (i.e. pump stations). As the developer, you are allowed one sanitary sewer service header per building without triggering this requirement. The plans generally include all site, grading, utility layout and include plan and profiles of the proposed sanitary line.


Stormwater Construction Drawings:
This is very similar to the wastewater construction plans but this is for storm water design. This design is reviewed by the Wastewater Department. The deliverables on this process consist of a set of stormwater design plans as well as a drainage report. You will need to meet all the requirements of the Denver Stormwater Triage checklist. This checklist can be found in the Storm Drainage Design & Technical Criteria Manual. These plans become a requirement if your project contains a detention facility, storm infrastructure, or any other major stormwater infrastructure.


Denver Water Review:
Generally speaking, Denver Water won’t make comments or review your conceptual plans. It’s frustrating but the way things are currently. I generally recommend to my clients to have a separate sit down in the concept phase with Denver Water if there is anything proposed beyond water services on-site. Denver will require a set of plans to be reviewed if your project needs any of the following: Public Water Main Extension, Fire Hydrant Installation, Fire sprinklers or any other major water infrastructure installation. The Denver Water review can be a lengthy process depending on what you are proposing to install, so its smart to get on this process right away if its required.


Storm Water Management Plan (SWMP):
A SWMP is required in Denver if you disturb over an acre of land in your development. Let me clarify that this is NOT a catch-all rule. I’ve seen sites smaller than an acre get forced into a SWMP due to being “High Risk”. These sites found asbestos while excavating and were, therefore, required. The SWMP deliverables are a narrative and erosion control set of plans. This will be the plan in which your contractor shall follow to ensure that no downstream properties are polluted by your development. A SWMP is sometimes called a Stormwater Pollution Prevention Plan (SWPPP) in other jurisdictions. City of Denver will review your SWMP for completeness and sometimes provide comments.


There can be a large amount of deliverables required by the City of Denver depending on your job. One of the most important things you can do as a new developer is to find a design team who you can trust and knows the jurisdiction you are developing in. In the City of Denver, ALC is a trusted design team to dozens of both seasoned and not-so-seasoned multifamily developers who expect a smooth process through City of Denver’s SDP requirements. Our project managers have worked with every project coordinator at the City and have the experience to get approval as quickly as possible.

Altitude Land Consultants help you navigate this process with greater ease, eliminate costly mistakes and loss of time.

 

Jefferson County Colorado Driveway Requirements

by: Eric Burtzlaff, PE

If you are planning to build a private home in Jefferson County, Colorado, I’m sure you have more than a few questions regarding the process. Approval from Jefferson County’s Planning and Zoning Department can be a taxing exercise for even the most seasoned engineers.

In my experience, one of the most important aspects from the Jefferson County’s perspective is your driveway design. The Jefferson County Standards on your driveway will push much of the location of your home, as well as the safety of egress and ingress in the slippery winter months. With that in mind, this article will discuss the Standards on your driveway from Jefferson County and elaborate on exactly why these requirements exist.

The driveway standards are as follows:
Rules of Thumb: Maximum of 10% slope (12% if south aspect); 14-ft width (10-ft paved)
A private driveway in Jefferson County may not be steeper than 10% grade or 10:1. This restraint is in place to avoid creating a slip and slide or unpassable driveway during the Colorado winter.

There is an exception in place for this standard. If your proposed driveway is naturally a southern facing driveway, you are allowed to go up to 12% grade. This is due to the your driveway receiving ample sun exposure and theoretically a faster ice melt. This standard also exists to allow safe travel of your driveway for any emergency vehicle which might need to get your residence.

Your driveway is required to be 14 feet wide throughout the entirety of the drive. The county requires a minimum 10′ all-weather travel surface as well as minimum 2′ shoulders on each side of the drive. You might think that this standard exists solely to allow two cars pass one another on your driveway. However, this standard is actually driven by fire safety. This is the minimum width for a fire truck (or other emergency vehicle) to access your home via your driveway.

The all-weather surface that this standard refers to can be gravel, asphalt, concrete or any other material you can manage to convince the fire department will hold the weight of their trucks.

Your driveway must also not have any radii less than 30′ at the centerline of your driveway.
This again is driven mostly by fire code. A fire truck is going to have a really hard time making any turn tighter than this standard. Also, this standard exists to prevent obscene hairpin turns on Jefferson County driveways. In the winter, such hairpin turns can spell real disaster when your truck start sliding down your drive.

There are a few exceptions to the rules. Firstly, if your driveway is under 50′ in length, none of these rules apply! Secondly, if your driveway is over 150′ in length, you are required to install a firetruck hammerhead (or turnaround) every 150′ of your drive. This allows the emergency vehicle that’s coming to your home to turn around if necessary.

I know my clients tend to get frustrated when I explain that their driveway won’t work the way they envisioned per the Jefferson County code. Just remember that these standards are really in place for your safety whether that be your winter safety or your safety in the event of a fire (or other emergency). You’ll be happy you followed these standards if you ever do come face-to-face with such an event.

Please see Jefferson County Roadway Design & Construction Manual, Section 3.7.8 to see these standards as written by Jefferson County.
Download

Block Sensitive Setbacks in Denver

By: Eric Burtzlaff, PE


One of the most important things that define the buildable area of a lot you are hoping to develop is the front setback of the lot. If you are developing in a zoning district or form that doesn’t require a block sensitive setback, this is not the blog for you. However, if you are developing a lot which requires a block sensitive setback, you will want to read on.
Firstly, lets define the block sensitive setback.
Block Sensitive Setback: The required front setback of the subject lot determined by adjacent existing structures located on the subject lot’s block.
I always recommend our clients get a survey completed prior to purchasing the land and certainly prior to starting your site development process. Our land survey team knows what information you’ll need to determine your block sensitive setback and appropriate determine your buildable area quickly and accurately.
Refer to this guide created by the City of Denver to answer commonly asked questions regarding the block sensitive setback requirement in the Denver Zoning Code.

DENVER ZONING BLOCK SENSITIVE SETBACK TIPS
If you have any questions or clarifications, you can always reach out directly to myself at 720.427.6161. Altitude Land Consultants has all the services in-house to navigate your project through the Site Development Process and will be happy to answer any questions you have in your feasibility phase free of charge.